The typical deadlines from the feasibility validation to start of work at microtunnel o pipe ramming depend mainly on 3 things: holder's permits/conditions, state of geotechnical engineering y degree of design definition. Even so, in standard projects it usually moves in these ranges:
Agile case (well-defined project): 4-8 weeks
When there is already a clear layout, access, permits in place and a defined solution between Microtunnel o Pipe jacking.Typical case (public/industrial work with processing): 8-16 weeks
This is the most frequent when it is necessary to close details, coordinate with third parties and prepare for implementation.Case with high complexity (strong conditioning factors): 16-24+ weeks
For example: interference from relevant services, limited access, work windows, owner approvals or the need to complete a geotechnical campaign.
What happens within that time frame (to make the meeting productive):
Technical closing (method, implementation, logistics, security): if it fits microtunnel o hinca, and what the well/site needs.
Permits and coordination (owners/management/operators).
Purchasing and mobilization (planning, resources, construction documentation).
If the project requires it, Eurohinca can provide support from Technical assistance and engineering to accelerate decisions and reduce iterations.
As a neutral industry reference on trenchless methodologies and best practices (non-commercial), you can consult the International Society for Trenchless Technology (ISTT): https://istt.com/