What are the typical lead times from feasibility validation to the start of work on microtunneling or ramming?

The typical deadlines from the feasibility validation to start of work at microtunnel o pipe ramming depend mainly on 3 things: holder's permits/conditions, state of geotechnical engineering y degree of design definition. Even so, in standard projects it usually moves in these ranges:

  • Agile case (well-defined project): 4-8 weeks
    When there is already a clear layout, access, permits in place and a defined solution between Microtunnel o Pipe jacking.

  • Typical case (public/industrial work with processing): 8-16 weeks
    This is the most frequent when it is necessary to close details, coordinate with third parties and prepare for implementation.

  • Case with high complexity (strong conditioning factors): 16-24+ weeks
    For example: interference from relevant services, limited access, work windows, owner approvals or the need to complete a geotechnical campaign.

What happens within that time frame (to make the meeting productive):

  1. Technical closing (method, implementation, logistics, security): if it fits microtunnel o hinca, and what the well/site needs.

  2. Permits and coordination (owners/management/operators).

  3. Purchasing and mobilization (planning, resources, construction documentation).

  4. If the project requires it, Eurohinca can provide support from Technical assistance and engineering to accelerate decisions and reduce iterations.