The well is sized for to house the equipment, to reliably transmit the thrust y operate smoothly (assembly, lifting, detritus/sludge management and access). In projects of pipe jacking (microtunneling), The design of wells conditions the viability and performance from the first meter.
1) Allowable thrust (attack shaft)
Design thrust (Ed):
Ed ≈ F_front (excavation pressure × area) + F_friction (τ perimetral × contact surface) + losses (curvature, joints, local friction). As an early guide, τ can be estimated between 5-20 kPa according to soil and lubrication.Well resistance: thrust rings/crown, screens y bottom slab must resist Ed × γ (γ 1.3-1.5).
Useful geometry: width = TBM + 1.0-1.5 m per side; length = push frame (6-10 m) + mounting area (≥ 6 m).
Hydraulic stability: check flotation, siphoning y punching with high NF.
For the construction detail of the pit and shoring, you can enlarge at Vertical wells.
2) Lifting and maneuvering
Lifting load (Q): TBM + trolleys + pipe sections + tools (consider sludge/water).
Certified equipment and points: beams, eyebolts, slings (coef. ≥ 7) and clear height sufficient for vertical descents without interfering with crowning.
Wellhead: hoisting light major components y pipe sections repetitive with safe guidance.
3) Site logistics (flow and safety)
Access: turning radii, truck bed and functional separation (sludge plant, energy, pipe stockpiling).
Sludge/detritus management: decanting, recirculation or transport; watertight wall bushings; bypass emergency.
Ancillary services: installed power (peaks of pushing and pumping), process water, ventilation and lighting.
HSE: handrails, lifelines, confined atmospheres, plan, plan for vertical rescue and of hydraulic emergency.
4) Quick sizing rules (indicative; validate in engineering)
| Variable | Attack well (MT/DP) | Reception well |
|---|---|---|
| Useful width/diameter | TBM + 1.0-1.5 m per side | DN + 0.6-1.0 m |
| Useful length | Push frame 6-10 m + reinforcement zone ≥ 6 m | Safe receiving area + protective screen |
| Bottom level | ≥ drive axle elevation - clearances | ≥ axle height with receiving berm |
| Permissible thrust | ≥ Ed × γ (γ 1.3-1.5) | Impact resistance/reception |
| Clearance height | Hook travel for Q for lifting | Removal of elements and safety |
The values depend on DN, L, Rmin, geotechnics, NF, The following information, method (microtunnel/Direct Pipe), equipment and specifications are available.
5) Three reference scenarios
Urban, DN 1200, L 180 m, saturated sands: Rectangular well shored with anti-flange slab; Ed high (front pressure + friction); dedicated sludge plant.
Crossing under highway, DN 600, L 90 m, silt with gravel: prefabricated circular shaft; moderate thrust; priority to maneuverability e hoisting frequent use of tubes.
Large DN 2200, L 240 m, competent clays: wide and short well for assembly; reinforced lifting points and crowning suitable for heavy cranes.
6) Minimum documentation required
Thrust calculation (front + friction + losses) and structural verification of rings/screens/slab.
Lifting plan (load matrix, radios, crane, certified accessories).
Logistics Layout (access, sludge plant, energy, ventilation, lighting).
HSE Plan (confinement, rescue, siphoning, falls to different levels).
As-built of wells and certificates of tests/lifting elements.
For normative criteria and European best practices for driving and related techniques, it is useful to consult the guide DWA-A 125E (Pipe Jacking and Related Techniques)
If you prefer a joint revision of your design, our team of Technical assistance and engineering can propose the dimensioning of the well and the layout if you already have a baseline data, you can request a quotation with the layout, geotechnics and DN/L foreseen.

