{"id":5593,"date":"2026-05-13T07:56:36","date_gmt":"2026-05-13T07:56:36","guid":{"rendered":"https:\/\/eurohinca.com\/?p=5593"},"modified":"2026-05-13T07:57:12","modified_gmt":"2026-05-13T07:57:12","slug":"what-documentation-is-provided-at-the-end-of-a-microtunnel-or-pile-driving-project","status":"publish","type":"post","link":"https:\/\/eurohinca.com\/en\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\/","title":{"rendered":"What documentation is provided at the end of a microtunneling or jacking project?"},"content":{"rendered":"<div data-elementor-type=\"wp-post\" data-elementor-id=\"5593\" class=\"elementor elementor-5593\" data-elementor-post-type=\"post\">\n\t\t\t\t<div class=\"elementor-element elementor-element-d6327ef e-flex e-con-boxed e-con e-parent\" data-id=\"d6327ef\" data-element_type=\"container\" data-e-type=\"container\">\n\t\t\t\t\t<div class=\"e-con-inner\">\n\t\t\t\t<div class=\"elementor-element elementor-element-0d3dfe2 elementor-widget elementor-widget-text-editor\" data-id=\"0d3dfe2\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"text-editor.default\">\n\t\t\t\t<div class=\"elementor-widget-container\">\n\t\t\t\t\t\t\t\t\t<p data-start=\"141\" data-end=\"482\">At the end of a work of <strong data-start=\"166\" data-end=\"199\">microtunneling or pipe jacking<\/strong>, In order to ensure the quality of the work, technical documentation must be provided to verify what has been executed, with what materials, under what controls and with what final results. This documentation is used for acceptance of the work, future operation, maintenance, quality traceability and contractual closure.<\/p><p data-start=\"484\" data-end=\"949\">In projects of <a class=\"decorated-link\" href=\"https:\/\/eurohinca.com\/en\/pipe-jacking-2\/\" target=\"_new\" rel=\"noopener\" data-start=\"500\" data-end=\"564\">pipe ramming<\/a> y <a class=\"decorated-link\" href=\"https:\/\/eurohinca.com\/en\/subway-terrestrial-applications\/\" target=\"_new\" rel=\"noopener\" data-start=\"567\" data-end=\"685\">microtunneling in terrestrial and subway applications<\/a>, The final documentation may vary according to the contract, the client, the project management and the type of infrastructure, but normally includes as-built drawings, progress records, topographical controls, quality, safety and environmental documentation.<\/p><h3 data-section-id=\"12h1yw5\" data-start=\"951\" data-end=\"995\">Standard closeout documentation<\/h3><p data-start=\"997\" data-end=\"1276\"><strong data-start=\"997\" data-end=\"1052\">As-built or final as-built drawings:<\/strong> They include the final position of the pipeline, elevations, alignment, slope, manholes, connections, approved changes and elements actually constructed. They are essential for future operations, maintenance or network extensions.<\/p><p data-start=\"1278\" data-end=\"1584\"><strong data-start=\"1278\" data-end=\"1326\">Topographic report and alignment control:<\/strong> includes checking the axis, elevation, slope, entry and exit points, deviations from the design and verifications made during execution. In works with demanding layouts, this control is key to validate the accuracy of the microtunnel.<\/p><p data-start=\"1586\" data-end=\"2016\"><strong data-start=\"1586\" data-end=\"1637\">Progress records and excavation parameters:<\/strong> may include dates of progress, lengths executed, thrust, torque, working pressures, incidents, stoppages, terrain changes, lubrication consumption, slurry management or specific data on the system used, especially in works with <a class=\"decorated-link\" href=\"https:\/\/eurohinca.com\/en\/closed-shield-epb\/\" target=\"_new\" rel=\"noopener\" data-start=\"1883\" data-end=\"1945\">EPB tunnel boring machine<\/a> o <a class=\"decorated-link\" href=\"https:\/\/eurohinca.com\/en\/closed-shield-hydroshield\/\" target=\"_new\" rel=\"noopener\" data-start=\"1948\" data-end=\"2015\">hydro shield<\/a>.<\/p><p data-start=\"2018\" data-end=\"2263\"><strong data-start=\"2018\" data-end=\"2064\">Certificates and traceability of materials:<\/strong> documentation of pipes, joints, voussoirs if applicable, mortars, lubricants, auxiliary elements, manufacturing certificates, technical data sheets and tests required by the project or applicable regulations.<\/p><p data-start=\"2265\" data-end=\"2526\"><strong data-start=\"2265\" data-end=\"2300\">Testing and quality control:<\/strong> tightness tests, dimensional checks, joint control, interior inspections, material reception records, non-conformities, corrective actions and evidence of compliance with the quality plan.<\/p><p data-start=\"2528\" data-end=\"2771\"><strong data-start=\"2528\" data-end=\"2567\">Health and safety documentation:<\/strong> HSE records, safety reports, work permits, inspections, specific training, access controls, protocols applied, incidents and preventive measures implemented during execution.<\/p><p data-start=\"2773\" data-end=\"3028\"><strong data-start=\"2773\" data-end=\"2801\">Environmental documentation:<\/strong> management of waste, sludge, pumping water, excavated material, environmental protection measures, removal records, authorizations, discharge controls if applicable, and compliance with the project's environmental conditions.<\/p><p data-start=\"3030\" data-end=\"3251\"><strong data-start=\"3030\" data-end=\"3080\">Report of incidents and lessons learned:<\/strong> summary of deviations, approved changes, constraints encountered, solutions adopted and recommendations for operation, maintenance or future phases of the project.<\/p><p data-start=\"3253\" data-end=\"3476\"><strong data-start=\"3253\" data-end=\"3300\">Final quality dossier or work dossier:<\/strong> an orderly grouping of drawings, reports, certificates, tests, records, relevant communications and contractual documentation necessary for the formal acceptance of the work.<\/p><h3 data-section-id=\"nyhell\" data-start=\"3478\" data-end=\"3522\">Why this documentation is important<\/h3><p data-start=\"3524\" data-end=\"3830\">The final documentation not only proves that the work has been executed. It also allows to know the real behavior of the terrain, to verify the accuracy achieved, to justify changes, to facilitate audits, to plan maintenance and to reduce uncertainties in future interventions on the infrastructure.<\/p><p data-start=\"3832\" data-end=\"4178\">At <a class=\"decorated-link\" href=\"https:\/\/eurohinca.com\/en\/infrastructure-crossings\/\" target=\"_new\" rel=\"noopener\" data-start=\"3835\" data-end=\"3917\">infrastructure crossings<\/a>, The final dossier is particularly important because it provides technical traceability of the action and facilitates coordination with network managers, administrations, utilities or main contractors.<\/p><p data-start=\"4180\" data-end=\"4468\"><strong data-start=\"4180\" data-end=\"4224\">Minimum checklist of final documentation:<\/strong> as-built drawings, topographic report, progress log, excavation parameters, material certificates, quality tests, HSE documentation, environmental management, incidents, non-conformities, approved changes and final construction dossier.<\/p><p data-start=\"4470\" data-end=\"4681\">Request information about the <a class=\"decorated-link\" href=\"https:\/\/eurohinca.com\/en\/request-offer\/\" target=\"_new\" rel=\"noopener\" data-start=\"4509\" data-end=\"4619\">technical documentation and site closure in trenchless projects<\/a> to define the necessary deliverables from the offer phase.<\/p>\t\t\t\t\t\t\t\t<\/div>\n\t\t\t\t<\/div>\n\t\t\t\t\t<\/div>\n\t\t\t\t<\/div>\n\t\t\t\t<\/div>","protected":false},"excerpt":{"rendered":"<p>Al finalizar una obra de microt\u00fanel o hinca de tuber\u00eda, debe entregarse una documentaci\u00f3n t\u00e9cnica que permita verificar qu\u00e9 se ha ejecutado, con qu\u00e9 materiales, bajo qu\u00e9 controles y con qu\u00e9 resultados finales. Esta documentaci\u00f3n sirve para recepci\u00f3n de obra, operaci\u00f3n futura, mantenimiento, trazabilidad de calidad y cierre contractual. En proyectos de hinca de tuber\u00eda [&hellip;]<\/p>\n","protected":false},"author":80,"featured_media":0,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[146],"tags":[],"class_list":["post-5593","post","type-post","status-publish","format-standard","hentry","category-preguntas-frecuentes"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.9 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Documentaci\u00f3n final en microt\u00fanel e hinca<\/title>\n<meta name=\"description\" content=\"Conozca qu\u00e9 documentaci\u00f3n se entrega al finalizar una obra de microt\u00fanel o hinca: as-built, topograf\u00eda, calidad, HSE y dossier final.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/eurohinca.com\/en\/what-documentation-is-provided-at-the-end-of-a-microtunnel-or-pile-driving-project\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Documentaci\u00f3n final en microt\u00fanel e hinca\" \/>\n<meta property=\"og:description\" content=\"Conozca qu\u00e9 documentaci\u00f3n se entrega al finalizar una obra de microt\u00fanel o hinca: as-built, topograf\u00eda, calidad, HSE y dossier final.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/eurohinca.com\/en\/what-documentation-is-provided-at-the-end-of-a-microtunnel-or-pile-driving-project\/\" \/>\n<meta property=\"og:site_name\" content=\"Eurohinca\" \/>\n<meta property=\"article:published_time\" content=\"2026-05-13T07:56:36+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-05-13T07:57:12+00:00\" \/>\n<meta name=\"author\" content=\"seouser\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"seouser\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\\\/\"},\"author\":{\"name\":\"seouser\",\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/#\\\/schema\\\/person\\\/2f455d0a7e0cf82717efa1161f5b8477\"},\"headline\":\"\u00bfQu\u00e9 documentaci\u00f3n se entrega al finalizar una obra de microt\u00fanel o hinca?\",\"datePublished\":\"2026-05-13T07:56:36+00:00\",\"dateModified\":\"2026-05-13T07:57:12+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\\\/\"},\"wordCount\":621,\"publisher\":{\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/#organization\"},\"articleSection\":[\"Preguntas frecuentes\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\\\/\",\"url\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\\\/\",\"name\":\"Documentaci\u00f3n final en microt\u00fanel e hinca\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/#website\"},\"datePublished\":\"2026-05-13T07:56:36+00:00\",\"dateModified\":\"2026-05-13T07:57:12+00:00\",\"description\":\"Conozca qu\u00e9 documentaci\u00f3n se entrega al finalizar una obra de microt\u00fanel o hinca: as-built, topograf\u00eda, calidad, HSE y dossier final.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/eurohinca.com\\\/es\\\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\\\/\"]}]},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Portada\",\"item\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"\u00bfQu\u00e9 documentaci\u00f3n se entrega al finalizar una obra de microt\u00fanel o hinca?\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/#website\",\"url\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/\",\"name\":\"Eurohinca\",\"description\":\"\",\"publisher\":{\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/#organization\",\"name\":\"Eurohinca\",\"url\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/eurohinca.com\\\/wp-content\\\/uploads\\\/2024\\\/01\\\/Logo-nuevo.png\",\"contentUrl\":\"https:\\\/\\\/eurohinca.com\\\/wp-content\\\/uploads\\\/2024\\\/01\\\/Logo-nuevo.png\",\"width\":512,\"height\":131,\"caption\":\"Eurohinca\"},\"image\":{\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/#\\\/schema\\\/logo\\\/image\\\/\"}},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/eurohinca.com\\\/es\\\/#\\\/schema\\\/person\\\/2f455d0a7e0cf82717efa1161f5b8477\",\"name\":\"seouser\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Final documentation in microtunneling and ramming","description":"Find out what documentation is delivered at the end of a microtunneling or driving work: as-built, topography, quality, HSE and final dossier.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/eurohinca.com\/en\/what-documentation-is-provided-at-the-end-of-a-microtunnel-or-pile-driving-project\/","og_locale":"en_US","og_type":"article","og_title":"Documentaci\u00f3n final en microt\u00fanel e hinca","og_description":"Conozca qu\u00e9 documentaci\u00f3n se entrega al finalizar una obra de microt\u00fanel o hinca: as-built, topograf\u00eda, calidad, HSE y dossier final.","og_url":"https:\/\/eurohinca.com\/en\/what-documentation-is-provided-at-the-end-of-a-microtunnel-or-pile-driving-project\/","og_site_name":"Eurohinca","article_published_time":"2026-05-13T07:56:36+00:00","article_modified_time":"2026-05-13T07:57:12+00:00","author":"seouser","twitter_card":"summary_large_image","twitter_misc":{"Written by":"seouser","Est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/eurohinca.com\/es\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\/#article","isPartOf":{"@id":"https:\/\/eurohinca.com\/es\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\/"},"author":{"name":"seouser","@id":"https:\/\/eurohinca.com\/es\/#\/schema\/person\/2f455d0a7e0cf82717efa1161f5b8477"},"headline":"\u00bfQu\u00e9 documentaci\u00f3n se entrega al finalizar una obra de microt\u00fanel o hinca?","datePublished":"2026-05-13T07:56:36+00:00","dateModified":"2026-05-13T07:57:12+00:00","mainEntityOfPage":{"@id":"https:\/\/eurohinca.com\/es\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\/"},"wordCount":621,"publisher":{"@id":"https:\/\/eurohinca.com\/es\/#organization"},"articleSection":["Preguntas frecuentes"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/eurohinca.com\/es\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\/","url":"https:\/\/eurohinca.com\/es\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\/","name":"Final documentation in microtunneling and ramming","isPartOf":{"@id":"https:\/\/eurohinca.com\/es\/#website"},"datePublished":"2026-05-13T07:56:36+00:00","dateModified":"2026-05-13T07:57:12+00:00","description":"Find out what documentation is delivered at the end of a microtunneling or driving work: as-built, topography, quality, HSE and final dossier.","breadcrumb":{"@id":"https:\/\/eurohinca.com\/es\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/eurohinca.com\/es\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\/"]}]},{"@type":"BreadcrumbList","@id":"https:\/\/eurohinca.com\/es\/que-documentacion-se-entrega-al-finalizar-una-obra-de-microtunel-o-hinca\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Portada","item":"https:\/\/eurohinca.com\/es\/"},{"@type":"ListItem","position":2,"name":"\u00bfQu\u00e9 documentaci\u00f3n se entrega al finalizar una obra de microt\u00fanel o hinca?"}]},{"@type":"WebSite","@id":"https:\/\/eurohinca.com\/es\/#website","url":"https:\/\/eurohinca.com\/es\/","name":"Eurohinca","description":"","publisher":{"@id":"https:\/\/eurohinca.com\/es\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/eurohinca.com\/es\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/eurohinca.com\/es\/#organization","name":"Eurohinca","url":"https:\/\/eurohinca.com\/es\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/eurohinca.com\/es\/#\/schema\/logo\/image\/","url":"https:\/\/eurohinca.com\/wp-content\/uploads\/2024\/01\/Logo-nuevo.png","contentUrl":"https:\/\/eurohinca.com\/wp-content\/uploads\/2024\/01\/Logo-nuevo.png","width":512,"height":131,"caption":"Eurohinca"},"image":{"@id":"https:\/\/eurohinca.com\/es\/#\/schema\/logo\/image\/"}},{"@type":"Person","@id":"https:\/\/eurohinca.com\/es\/#\/schema\/person\/2f455d0a7e0cf82717efa1161f5b8477","name":"seouser"}]}},"_links":{"self":[{"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/posts\/5593","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/users\/80"}],"replies":[{"embeddable":true,"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/comments?post=5593"}],"version-history":[{"count":4,"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/posts\/5593\/revisions"}],"predecessor-version":[{"id":5597,"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/posts\/5593\/revisions\/5597"}],"wp:attachment":[{"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/media?parent=5593"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/categories?post=5593"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/eurohinca.com\/en\/wp-json\/wp\/v2\/tags?post=5593"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}